The table below shows the integration times for GP2GP transfers received.
Month | GP2GP transfers received | Integrated within 3 days | Integrated within 8 days | Not integrated within 8 days (paper copy requested) |
---|---|---|---|---|
Month August 2024 | GP2GP transfers received 42 | Integrated within 3 days 61.9% | Integrated within 8 days 38.1% | Not integrated within 8 days (paper copy requested) 0% |
Month July 2024 | GP2GP transfers received 26 | Integrated within 3 days 30.8% | Integrated within 8 days 42.3% | Not integrated within 8 days (paper copy requested) 26.9% |
Month June 2024 | GP2GP transfers received 38 | Integrated within 3 days 78.9% | Integrated within 8 days 21.1% | Not integrated within 8 days (paper copy requested) 0% |
Month May 2024 | GP2GP transfers received 36 | Integrated within 3 days 52.8% | Integrated within 8 days 30.6% | Not integrated within 8 days (paper copy requested) 16.7% |
Month April 2024 | GP2GP transfers received 49 | Integrated within 3 days 73.5% | Integrated within 8 days 26.5% | Not integrated within 8 days (paper copy requested) 0% |
Month March 2024 | GP2GP transfers received 36 | Integrated within 3 days 38.9% | Integrated within 8 days 50% | Not integrated within 8 days (paper copy requested) 11.1% |
Data updated: September 2024
New data is added around 15th of each month