Orchard Surgery - M83038 integration times
Integration times for registering practice
The table below shows the integration times for GP2GP transfers received.
Month | GP2GP transfers received | Integrated within 3 days | Integrated within 8 days | Not integrated within 8 days (paper copy requested) |
---|---|---|---|---|
Month October 2024 | GP2GP transfers received 39 | Integrated within 3 days 84.6% | Integrated within 8 days 10.3% | Not integrated within 8 days (paper copy requested) 5.1% |
Month September 2024 | GP2GP transfers received 36 | Integrated within 3 days 30.6% | Integrated within 8 days 69.4% | Not integrated within 8 days (paper copy requested) 0% |
Month August 2024 | GP2GP transfers received 42 | Integrated within 3 days 61.9% | Integrated within 8 days 38.1% | Not integrated within 8 days (paper copy requested) 0% |
Month July 2024 | GP2GP transfers received 26 | Integrated within 3 days 30.8% | Integrated within 8 days 42.3% | Not integrated within 8 days (paper copy requested) 26.9% |
Month June 2024 | GP2GP transfers received 38 | Integrated within 3 days 78.9% | Integrated within 8 days 21.1% | Not integrated within 8 days (paper copy requested) 0% |
Month May 2024 | GP2GP transfers received 36 | Integrated within 3 days 52.8% | Integrated within 8 days 30.6% | Not integrated within 8 days (paper copy requested) 16.7% |
Data updated: November 2024
New data is added around 15th of each month