Lee Road Surgery - G85046 integration times
Integration times for registering practice
The table below shows the integration times for GP2GP transfers received.
Month | GP2GP transfers received | Integrated within 3 days | Integrated within 8 days | Not integrated within 8 days (paper copy requested) |
---|---|---|---|---|
Month April 2025 | GP2GP transfers received 70 | Integrated within 3 days 61.4% | Integrated within 8 days 12.9% | Not integrated within 8 days (paper copy requested) 25.7% |
Month March 2025 | GP2GP transfers received 70 | Integrated within 3 days 24.3% | Integrated within 8 days 70% | Not integrated within 8 days (paper copy requested) 5.7% |
Month February 2025 | GP2GP transfers received 69 | Integrated within 3 days 43.5% | Integrated within 8 days 46.4% | Not integrated within 8 days (paper copy requested) 10.1% |
Month January 2025 | GP2GP transfers received 93 | Integrated within 3 days 75.3% | Integrated within 8 days 24.7% | Not integrated within 8 days (paper copy requested) 0% |
Month December 2024 | GP2GP transfers received 50 | Integrated within 3 days 64% | Integrated within 8 days 36% | Not integrated within 8 days (paper copy requested) 0% |
Month November 2024 | GP2GP transfers received 67 | Integrated within 3 days 10.4% | Integrated within 8 days 34.3% | Not integrated within 8 days (paper copy requested) 55.2% |
Data updated: May 2025
New data is added around 15th of each month