Manor Brook Pms - G83001 integration times
Integration times for registering practice
The table below shows the integration times for GP2GP transfers received.
Month | GP2GP transfers received | Integrated within 3 days | Integrated within 8 days | Not integrated within 8 days (paper copy requested) |
---|---|---|---|---|
Month April 2025 | GP2GP transfers received 29 | Integrated within 3 days 100% | Integrated within 8 days 0% | Not integrated within 8 days (paper copy requested) 0% |
Month March 2025 | GP2GP transfers received 58 | Integrated within 3 days 96.6% | Integrated within 8 days 0% | Not integrated within 8 days (paper copy requested) 3.4% |
Month February 2025 | GP2GP transfers received 42 | Integrated within 3 days 97.6% | Integrated within 8 days 2.4% | Not integrated within 8 days (paper copy requested) 0% |
Month January 2025 | GP2GP transfers received 54 | Integrated within 3 days 88.9% | Integrated within 8 days 11.1% | Not integrated within 8 days (paper copy requested) 0% |
Month December 2024 | GP2GP transfers received 58 | Integrated within 3 days 84.5% | Integrated within 8 days 8.6% | Not integrated within 8 days (paper copy requested) 6.9% |
Month November 2024 | GP2GP transfers received 72 | Integrated within 3 days 70.8% | Integrated within 8 days 23.6% | Not integrated within 8 days (paper copy requested) 5.6% |
Data updated: May 2025