London Road Surgery - F81041 integration times
Integration times for registering practice
The table below shows the integration times for GP2GP transfers received.
| Month | GP2GP transfers received | Integrated within 3 days | Integrated within 8 days | Not integrated within 8 days (paper copy requested) |
|---|---|---|---|---|
| Month October 2025 | GP2GP transfers received 32 | Integrated within 3 days 56.2% | Integrated within 8 days 3.1% | Not integrated within 8 days (paper copy requested) 40.6% |
| Month September 2025 | GP2GP transfers received 37 | Integrated within 3 days 67.6% | Integrated within 8 days 27% | Not integrated within 8 days (paper copy requested) 5.4% |
| Month August 2025 | GP2GP transfers received 27 | Integrated within 3 days 92.6% | Integrated within 8 days 7.4% | Not integrated within 8 days (paper copy requested) 0% |
| Month July 2025 | GP2GP transfers received 30 | Integrated within 3 days 100% | Integrated within 8 days 0% | Not integrated within 8 days (paper copy requested) 0% |
| Month June 2025 | GP2GP transfers received 20 | Integrated within 3 days 90% | Integrated within 8 days 10% | Not integrated within 8 days (paper copy requested) 0% |
| Month May 2025 | GP2GP transfers received 25 | Integrated within 3 days 76% | Integrated within 8 days 12% | Not integrated within 8 days (paper copy requested) 12% |
Data updated: November 2025
New data is added around 15th of each month