Park Green Surgery - B87006 integration times
Integration times for registering practice
The table below shows the integration times for GP2GP transfers received.
Month | GP2GP transfers received | Integrated within 3 days | Integrated within 8 days | Not integrated within 8 days (paper copy requested) |
---|---|---|---|---|
Month October 2024 | GP2GP transfers received 10 | Integrated within 3 days 70% | Integrated within 8 days 30% | Not integrated within 8 days (paper copy requested) 0% |
Month September 2024 | GP2GP transfers received 5 | Integrated within 3 days 40% | Integrated within 8 days 20% | Not integrated within 8 days (paper copy requested) 40% |
Month August 2024 | GP2GP transfers received 0 | Integrated within 3 days n/a | Integrated within 8 days n/a | Not integrated within 8 days (paper copy requested) n/a |
Month July 2024 | GP2GP transfers received 3 | Integrated within 3 days 33.3% | Integrated within 8 days 33.3% | Not integrated within 8 days (paper copy requested) 33.3% |
Month June 2024 | GP2GP transfers received 11 | Integrated within 3 days 18.2% | Integrated within 8 days 0% | Not integrated within 8 days (paper copy requested) 81.8% |
Month May 2024 | GP2GP transfers received 2 | Integrated within 3 days 100% | Integrated within 8 days 0% | Not integrated within 8 days (paper copy requested) 0% |
Data updated: November 2024
New data is added around 15th of each month