The table below shows the integration times for GP2GP transfers received.
| Month | GP2GP transfers received | Integrated within 3 days | Integrated within 8 days | Not integrated within 8 days (paper copy requested) |
|---|---|---|---|---|
| Month October 2025 | GP2GP transfers received 19 | Integrated within 3 days 68.4% | Integrated within 8 days 31.6% | Not integrated within 8 days (paper copy requested) 0% |
| Month September 2025 | GP2GP transfers received 23 | Integrated within 3 days 69.6% | Integrated within 8 days 26.1% | Not integrated within 8 days (paper copy requested) 4.3% |
| Month August 2025 | GP2GP transfers received 11 | Integrated within 3 days 90.9% | Integrated within 8 days 9.1% | Not integrated within 8 days (paper copy requested) 0% |
| Month July 2025 | GP2GP transfers received 26 | Integrated within 3 days 69.2% | Integrated within 8 days 30.8% | Not integrated within 8 days (paper copy requested) 0% |
| Month June 2025 | GP2GP transfers received 10 | Integrated within 3 days 100% | Integrated within 8 days 0% | Not integrated within 8 days (paper copy requested) 0% |
| Month May 2025 | GP2GP transfers received 15 | Integrated within 3 days 60% | Integrated within 8 days 26.7% | Not integrated within 8 days (paper copy requested) 13.3% |
Data updated: November 2025