The table below shows the integration times for GP2GP transfers received.
Month | GP2GP transfers received | Integrated within 3 days | Integrated within 8 days | Not integrated within 8 days (paper copy requested) |
---|---|---|---|---|
Month October 2024 | GP2GP transfers received 36 | Integrated within 3 days 83.3% | Integrated within 8 days 16.7% | Not integrated within 8 days (paper copy requested) 0% |
Month September 2024 | GP2GP transfers received 17 | Integrated within 3 days 70.6% | Integrated within 8 days 29.4% | Not integrated within 8 days (paper copy requested) 0% |
Month August 2024 | GP2GP transfers received 18 | Integrated within 3 days 100% | Integrated within 8 days 0% | Not integrated within 8 days (paper copy requested) 0% |
Month July 2024 | GP2GP transfers received 9 | Integrated within 3 days 100% | Integrated within 8 days 0% | Not integrated within 8 days (paper copy requested) 0% |
Month June 2024 | GP2GP transfers received 19 | Integrated within 3 days 68.4% | Integrated within 8 days 31.6% | Not integrated within 8 days (paper copy requested) 0% |
Month May 2024 | GP2GP transfers received 36 | Integrated within 3 days 88.9% | Integrated within 8 days 0% | Not integrated within 8 days (paper copy requested) 11.1% |
Data updated: November 2024